We Wai Kai Nation reposted this
Our quarry site is experiencing significant growth and development as we advance on our $24.4 million contract with Aecon-EBC for BC Hydro’s John Hart Dam Seismic Upgrades Project. This expansion of almost 1 hectare was necessary for an increase to our storage capacity for rip rap products before they are transported to the construction site. It created about 500 m3 of merchantable timber, and the stumps are being re-purposed to become fish habitat in John Hart Lake. 🔬 Scope of Work: Way Key LP is focused on supplying rip rap products to Aecon-EBC. Production capacity has increased substantially since mid-July, reflecting a notable rise in monthly output. ⏱ Timeline: The project commenced in summer of 2023 and is slated for completion in 2026. 💼 Community Involvement: The quarry has created jobs for community members, with over $900,000 paid in wages to date to Indigenous employees by Way Key Sand & Gravel. #BCEarthworks #Grading #Clearing #JohnHartDam Roga Group