Upper Trishuli-1 Hydropower Project (UT-1:216 MW) The project has made significant strides with several key developments. The Head Race Tunnel (HRT), spanning nearly 9.5 km, is now approximately 72% complete, with a major breakthrough achieved in June 2024. Foundation works for the weir area are underway, including partial wall concreting. The surge chamber excavation has been completed, and progress continues on the surge shaft and vertical pressure shaft. Concreting work in the powerhouse is advancing across various levels. Concurrently, design works and reviews are ongoing, and the mobilization of the hydromechanical (HM) and electromechanical (EM) contractors is in progress, along with continued factory acceptance testing (FAT) inspections. #Hydropower #RenewableEnergy #SustainableDevelopment #Engineering #CleanEnergy #ProjectUpdate #Nepal #ConstructionProgress #Jadeconsult #Tractebel #IFC #ADB # #Uppertrishuli-1 #AIIB #K-EXIM #KDB #CDC #FMO #PROPARCO #OFID
-