The UK Atomic Energy Authority has formally opened bidding for separate engineering and construction partners to build the country’s first big fusion energy plant.

The commercial protype plant will be built at the former West Burton coal-fired power station site in Nottinghamshire, and aims to demonstrate net energy from fusion in the 2040s.

Fusion is based on the same physical reactions that power the sun and stars, combining two hydrogen atoms to release large amounts of energy.

Importantly, the Spherical Tokamak for Energy Production (STEP) plant will also pave the way for an industry capable of delivering commercial fusion for decades.

Both contract terms will be an initial three-year period, followed by three optional extension periods of four, six and seven years.

The successful engineering and construction partners will deliver work in successive packages, cumulatively worth hundreds of millions of pounds during the initial contract period until 2029. Contracts will then build progressively in line with the development of the prototype plant.

According to the tender invitation the maximum contract duration for both contracts will be 20 years with an estimated value of £10bn each across this period.

This appointed teams will work collaboratively with UKAEA, under joint incentivisation mechanisms.

These partners will be core to delivery of the programme, as well as securing market-leading experience and knowledge.

Atkins and energy transition specialists Assystem have been working as engineering delivery partners to develop the concept design for STEP.

The appointed engineering and construction partners will develop a fully-formed major programme to deliver a full plant design, a viable supply chain and seek the consents needed for construction.

The construction partner will be tasked with delivering a site development programme, including innovative building designs focused on cost, schedule, safety and sustainability.

Applications are due in by 17 July with an initial three-year contract start date of May 2026. For more details click here.

Latest news

Competition concern about circular ducting in Midlands

Lindab take-over of HAS-Vent raises competition concern in Nottingham and Stoke-on-Trent
2 days ago

Historic facade contractor owed suppliers £2.3m

Charles Henshaw & Sons owed money to more than 100 trade creditors
2 days ago

Ultra-low carbon cement factory production to start this autumn

Material Evolution industry-changing technology moves from lab to factory production
2 days ago

ISG takes plunge at historic Brum baths restoration

Exterior restoration work to start this month at Moseley Road Baths
2 days ago

Winvic clocks up 100m sq ft of shed space with latest order

Magna Park warehouse job marks historic milestone for 23 year-old firm
2 days ago

Site secured for nuclear research “super cluster”

Nuclear research centre planned for Gloucestershire site
2 days ago

Vistry seals £60m deal to build 270 homes in Ordsall

£3m enabling works to start on Salford 10-acre brownfield site
2 days ago

Robertson pulls-out of £71m school campus scheme

Peterhead Community Campus project facing further delays
3 days ago

Equans reduces losses to £39m after new build homes exit

Firm pins hopes on profitable path through social housing refurb and net-zero retrofits
3 days ago

Scottish Water puts firms on alert for £6.3bn framework

Bid race to start in November for civils infrastructure and MEICA asset delivery partners
3 days ago

Waitrose back to building with bold £1bn store plan

Plan to build 100 convenience stores and four large supermarkets in five years
3 days ago

Octavius seals deal for £27m Essex road job

New A1331 dual carriageway near Colchester paves way for new homes
3 days ago

Curo Construction to take on former Henry job

Work to restart on The Charter in Gravesend
4 days ago

Leisure centre builder Pellikaan revenue almost halves

South London-based contractor branches out with first school job
3 days ago

Costain profits double to £17m in first half

Contractor launches share buyback after strong cash performace
4 days ago

Six bag £2bn MoD single living framework places

B+K, Kier, Laing O'Rourke and Reds10 among firms joining new alliance
5 days ago

Bugler in talks to replace failed builder ARJ on flats job

Dacorum Council acts to restart stalled £20m Hemel Hempstead project
4 days ago

Green light for first UK flying taxi base

Construction to start this Autumn on Bicester vertiport
4 days ago

Go-ahead for Glasgow 36-floor student tower

Watkin Jones gets go-ahead for 780 student rooms tower and office block
4 days ago

Wavensmere submits plans for Wolverhampton £150m scheme

Canalside South will regenerate derelict site by the waterfront
4 days ago

Halsall Construction went down owing suppliers £7m

Bath based contractor owed money to more than 400 subcontractors
5 days ago

Kier to build Southampton Uni teaching hub

Work to start in New Year on North East Quadrant site subject to full planning
5 days ago

Hill submits plan for over 1,600 North London homes

£500m Willesden high rise scheme will consist of 11 blocks
5 days ago

Browne bags £130m Thames Water leak-busting contract

Infrastructure specialist wins latest mains renewal deal
5 days ago

Lovell lands deal to revamp Sutton estate

Construction to start next May on rebuild of town centre estate
5 days ago

Applications open for latest Women into Home Building programme

Latest round of HBF scheme comes after closure of Women into Construction
5 days ago

Keltbray sells infrastructure business to private equity firm

New owner EMK Capital for £378m-turnover division
6 days ago

West Midlands modular firm falls into administration

122 jobs axed as Modpods International enters administration
6 days ago

Muckshifters called up for £2.2bn Abingdon reservoir

Thames Water starts early engagement with earthworks firms for vast Oxfordshire job
6 days ago

Race starts for £1.5bn Parliament estate upkeep deal

Invitation to tender for seven-year multi-lot framework
6 days ago

Contractor services