400 Central Residences in St. Petersburg, FL held its structural Topping Out Party on September 16th, 2024. Our crew was part of this event and got to sign the beam! Currently, Ackerman Plumbing is pushing to finish Phase 1 of this project with only half of final floor and the roof left to pour. Phase 2 is coming to a head as we prepare to rough-in Domestic Water, Condensate, and Natural Gas on levels 40-43; meanwhile, we are down on Level 1 roughing-in Storm and Sanitary while we wait for structure reshores to come down on Level 43. Simultaneously, In-wall Units are being roughed-in on Level 39. Phase 3 is fully underway as we install trim and fixtures on Level 18.
-
-
-
-
-
+1
Owner
4moGood work! Just out of curiosity is the structure cast in place? If so what through floor penetration devices are you guys utilizing?