More than 30 contractors and vendors worked with ConocoPhillips on constructing Zia Hills Central Facility 2 (CF2), installing more than 174 pieces of equipment, 40,000 feet of pipe and 260,000 feet of cable. Despite disruptions from the COVID-19 pandemic, this entire process was safely completed on time and under budget without a single recordable incident. Click through to see a time lapse video: https://bit.ly/3z74dvU
In this story we can see how the completion of a project can be done on time and under budget even it was hampered by sudden pandemic.
In another part of the earth a project was signed between owner and contractor but there was no mobilization for 7-8 months. Only after internal Joint Operation Agreement was discussed and signed the moving-in process was commenced.
But that wasn't the end of story. Even it wasn't hampered by pandemic the project had to deal with land problems because there are so many obstacles like graves, residential areas, historical monuments, immovable local government's assets and so on which automatically hampered the completion time of this construction.
Even it was planned by hi-tech system including the material calculation but in practice from 4 sacks of cement that had to be used based on material calculation only 2 were used while the other 2 were not used and the money that should be used to buy the other 2 sacks went nowhere to be found (hey, story like this is common in this another part of the world). And it was not just happened to cement but also happened to pole, lamp, steel, you name it. Construction failure is common and accident is just a matter of time.
PS.: True story.
#Win PCs, #Prodom,#A2dMs, Go to the certificate #CompEx#Electrical QA/QC Engineer# Pre-com Dossier preparation# cathodic protection for QC cross country pipe line and storage Tank
More than 30 contractors and vendors worked with ConocoPhillips on constructing Zia Hills Central Facility 2 (CF2), installing more than 174 pieces of equipment, 40,000 feet of pipe and 260,000 feet of cable. Despite disruptions from the COVID-19 pandemic, this entire process was safely completed on time and under budget without a single recordable incident. Click through to see a time lapse video: https://bit.ly/3SX6hOi
On March 23, 2005, a series of explosions occurred at the BP Texas City, Texas, refinery during the restarting isomerization unit— killing 15 workers and injuring 180 others. The explosions occurred when a distillation tower flooded with hydrocarbons and was overpressurized, causing a geyser-like release from the vent stack. BP formed the BP U.S. Refineries Independent Safety Review Panel also referred as Banker Panel.
Excerpt from the Baker Panel report:
“BP has emphasized personal safety in recent years and has achieved significant improvement in personal safety performance but BP did not emphasize process safety.
BP mistakenly interpreted improving personal injury rates as an indication of acceptable process safety performance at its U.S. refineries.
BP's reliance on this data, combined with an inadequate process safety understanding, created a false sense of confidence that BP was properly addressing process safety risks."
Are you worried about misclassifying contractors and facing penalties?
We're introducing Oyster Shell which evaluates misclassification risk and offers protection up to $500,000 🦪
Now you can make more informed decisions to hire contractors and avoid penalties and unwanted expenses 💸 Building a global team has never been this easy (and safe ✨)
Learn more here: https://bit.ly/3KezAHk
Are you worried about misclassifying contractors and facing penalties?
We're introducing Oyster Shell which evaluates misclassification risk and offers protection up to $500,000 🦪
Now you can make more informed decisions to hire contractors and avoid penalties and unwanted expenses 💸 Building a global team has never been this easy (and safe ✨)
Learn more here: https://bit.ly/3KezAHk
The Importance of pertinent Pre-Startup Safety Reviews when resuming operation after shutdown and maintenance activities in a hazardous plant. 📣 ⚒
Beyond complying with regulations it can help identify and mitigate hazards, validate critical procedures, enhance your emergency preparedness, facilitate communication and coordination among stakeholders, and support ongoing efforts to improve safety and operational efficiency.
💡 Pro Tip 💡
PSSR is a great opportunity for lessons learned from past incidents or near-misses to be incorporated into startup procedures and practices, that can support a culture of continuous improvement in hazardous plant safety and operations.
Exxon owned Gravenchon refinery is fortunate to have not had more damage and injury with the fire incident.
https://lnkd.in/dH7YeH8j#pssr#psm#incidentinvestigation#hse#processsafetymanagement
Do you work in Chemicals or Petrochem? Are you part of Refinery Shutdowns or Turnarounds?
If so, this is the conference for you! Join us in New Orleans, LA from July 30th - August 1st! Our team specializes in Contractor & Asset Management and would love to chat.
#chemicals#petrochem#AES32#contractors#contractormanagement#assets#assetmanagement
Exciting News! NHD is sponsoring the 16th Edition of the Chem/Petrochem and Refinery Shutdowns and Turnarounds Conference, happening in New Orleans, LA from July 30 to August 1, 2024! Event Website: https://lnkd.in/ebPr253g
Join us at this event to gain insights into continuous improvement in shutdowns and outages throughout their entire lifecycle. NHD provides an intelligent platform for contractor management, ensuring seamless collaboration between clients and suppliers from project planning to payment for asset-intensive operations.
one of the implications of overturning Chevron deference may be less regulatory capture of government agencies. Typically, when an agency is tasked with creating regulations, it depends heavily on industry stakeholders for input. Over time and political cycles, this leads to revolving door between regulated industry and agency appointments and hires.
Currently, numerous emergency crews are responding to a large power outage at the BP refinery in Whiting, Indiana. The outage has prompted employees to evacuate of the refinery, with heavy flare activity observed. Reports indicate multiple streets near the refinery have been shut down. Officials state that this restoration process could take several hours. Additional smoke and flames are expected as a precautionary measure to burn off products smoke and flames can be seen miles away
Could be an accident or event in a larger set of patterned events. So how would you know? How well do you connect dots in an accurate manner with evidence based verification? Here is a good exercise for you.
Othniel Max Daves
Quality, Health, Safety and Environment | 7 years experience in Oil&Gas industry | IOSH Institute Member | ASSP Member | ISO (9001, 14001 and 45001) Auditor | Welding, NDT and Coating inspections.
Fire and explosion occurrd on March 23, 2005, at the BP Texas City refinery.
It was a result of a catastrophic failure during the startup of the isomerization (isom) unit. The incident was one of the most severe industrial disasters in the U.S., killing 15 workers and injuring over 180 others.
Key findings from the investigation:
1. Overfilling of the Unit: During the startup process, a distillation tower in the isom unit was overfilled with hydrocarbons. This was followed by a malfunction that caused the release of a large quantity of flammable liquid into the atmosphere.
2. Vapor Cloud Formation: The flammable liquid formed a vapor cloud that spread across the area. When an ignition source was encountered, the vapor cloud exploded.
3. Failure of Safety Systems: The investigation revealed multiple failures in the safety management systems. Alarm systems did not function properly, and safety controls, such as proper procedures for startup, were inadequate.
4. Human Error: There were significant issues related to human factors, such as inadequate training of operators, lack of supervision during the startup, and failure to recognize hazards.
5. Cost-Cutting and Organizational Failures: The report highlighted BP's history of cost-cutting measures that reduced funding for maintenance and safety improvements at the refinery. This created a dangerous operating environment with outdated equipment and insufficient safety culture.
6. Outdated Equipment: The equipment used in the isom unit was outdated, and critical safety instrumentation that could have prevented the accident was either not installed or not functioning.
7. Flammable Materials Near Trailers: Many of the workers who died were located in trailers positioned too close to hazardous operations, which was a violation of standard safety practices.
Investigative bodies emphasized the need for systemic improvements in BP's safety culture and management practices to prevent such incidents in the future. The disaster led to reforms within the industry, with BP being fined and facing numerous lawsuits.
#incident#accident#fire#explosion#investigation#oil#gas#refinery#learning
By batching your well decommissioning with that of other operators as part of a multi-well, multi-operator P&A Club, everyone benefits from long-term cost minimisation, increased operational safety and greater efficiencies of scale.
What's in it for you?
🌏 Access to proven international experience.
💷 Transparent pricing, delivering long-term cost minimisation and predictability
✔️ Operators can assign resources to value-adding activities, knowing well abandonment is in safe hands
⌚ Short-notice access to dedicated abandonment assets
🗂️ The ability to add a single, or small number, of wells to reap the benefits of scope aggregation.
Learn more and get in touch with us on our website (link in comments).
#wellsafesolutions#wearewellsafe#decommissioning
-
4moIn this story we can see how the completion of a project can be done on time and under budget even it was hampered by sudden pandemic. In another part of the earth a project was signed between owner and contractor but there was no mobilization for 7-8 months. Only after internal Joint Operation Agreement was discussed and signed the moving-in process was commenced. But that wasn't the end of story. Even it wasn't hampered by pandemic the project had to deal with land problems because there are so many obstacles like graves, residential areas, historical monuments, immovable local government's assets and so on which automatically hampered the completion time of this construction. Even it was planned by hi-tech system including the material calculation but in practice from 4 sacks of cement that had to be used based on material calculation only 2 were used while the other 2 were not used and the money that should be used to buy the other 2 sacks went nowhere to be found (hey, story like this is common in this another part of the world). And it was not just happened to cement but also happened to pole, lamp, steel, you name it. Construction failure is common and accident is just a matter of time. PS.: True story.