Rain or shine, progress marches on!! We're thrilled to announce that we've completed the entire building pad for the new Chapel Hill ISD Jr High. All lifts have been tested, and the pad is primed and ready for action.  Next up, grading the roads and parking lots, and building up the football field area. Our team has been digging footings, setting rebar, and pouring the footings for Area B, our starting point. We are currently installing underground sanitary sewer and manholes throughout the west end of the site. Harris Craig Architects #buildingtexasschools