#YCCProjectUpdate – Our Holland Tunnel Project Team has made significant progress these past few months! The project team recently installed a truss atop the Holland Tunnel Toll Booth building. The building was jacked to engage with the new truss which allowed the removal of the columns underneath on the ground level to have 5 conjunctive lanes of traffic going into the tunnel. The new truss is the main structural support system that helps distribute load throughout the structure. The truss was set on the existing column after they were reinforced along with the reinforcement of the existing footings. In addition, the truss was covered with standing seam panels with the epic bronze color to match the existing plaza colors, so the truss blended with the roof and showed that it had been part of the original building. #HollandTunnel #NYCconstruction #NJconstruction #BuildingQualitySince1945
-