Watch: Lack of focus behind sluggish KAVACH coverage in Railways | Data Point

The Hindu estimates the pace with which KAVACH needs to be deployed across the India Railway network if the project has to be completed in ten years.

Updated - June 29, 2024 01:46 pm IST

Published - June 28, 2024 02:22 pm IST

The Kanchanjunga Express train crash has set off alarm bells with experts pointing to the sluggish pace with which KAVACH is being implemented.

In five years since its inception in FY19, KAVACH has been deployed only across 1,465 route kilometres and in 139 engines. At this rate, implementing the system will take between 50 to 100 more years.

In this video, The Hindu looks at the data to understand whether the issue lies with funding or the government’s lack of focus. The Hindu also estimates the pace with which KAVACH needs to be deployed across the India Railway network if the project has to be completed in ten years.

Presentation and production: Sambavi Parthasarathy

Ideation and Data support: Vignesh Radhakrishnan, Mahima Rao

Videography: Thamodharan B

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.

  翻译: