Syblon Reid’s Post

View organization page for Syblon Reid, graphic

1,375 followers

The project at Grizzly Tunnel focused on clearing accumulated debris from the rock trap. Activities included setting up equipment, removing the surge shaft grating, accessing the tunnel through the penstock hatch, installing safety measures, lighting, and a bypass system. Spoils were transported using a crane, skip box, and dump truck to Staging Area 1 at Lower Bucks. The process ensured thorough debris removal while prioritizing safety and environmental considerations. #syblonreid #contractorservices #engineeringcontractors #generalengineering #constructionindustry #constructioncrew #folsomca