Slowed down roll-out of Kavach may be attributed to several reasons

The Kavach system, despite having obtained the highest Safety Integrity Level (SIL)-4 in 2017-18, was not allowed to be deployed quickly for reasons that were not explained, sources said

Updated - July 11, 2024 05:23 pm IST

Published - July 09, 2024 08:27 am IST - HYDERABAD

A loco pilot testing the functioning of Kavach in South Central Railway (SCR), in Vikarabad district. The image is used for representative purpose only.

A loco pilot testingthe functioning of Kavach in South Central Railway (SCR), in Vikarabad district. The image is used for representative purpose only. | Photo Credit: NAGARA GOPAL

The slow roll-out across the Indian Railways of Kavach, the indigenously developed Train Collision Avoidance System (TCAS), was due to the Railway Board’s decision to opt for the expensive European Train Control System (ETCS), sources said. The COVID-19 pandemic put a brake on this move subsequently, senior officials in the Indian Railways, seeking anonymity, said.

They said the Kavach system, despite being extensively tested during trial runs under various conditions, including on automatic signalling routes, and having obtained the highest Safety Integrity Level (SIL)-4 in 2017-18 itself, was not allowed to be deployed quickly for reasons that were not explained. The original design team was side-lined after the decision to opt for ETCS, the sources said.

The Kavach Version 3.2 has so far been implemented in about 1,465 km of the South Central Railway, including the Wadi-Vikarabad-Sanatnagar and Vikarabad-Bidar sections, covering 133 stations, 29 level crossing gates, and 150 locomotives.

The latest Kavach Version 4 is currently under testing and deployment over 3,000 km in the Delhi-Mumbai and Delhi-Kolkata sections.

The system was conceived by the Indian Railways’ own Lucknow-based Research Design and Standards Organisation, after the Anil Kakodkar Committee of 2012 recommended an “advanced radio based signalling system similar to level ETCS ‘level 2’ for the entire trunk route length of 19,000 km within five years”.

The proposed new system was to provide safety and enhance existing line capacity, based on which it was decided ETCS-2 or equivalent was preferable. Kavach was originally cleared for field concept trials back in 2012, and field trials for the development of the “full-fledged SIL 4 compliant multi-vendor interoperable version” started in 2013 between the Tandur-Kurgunta section in Karnataka for 32 km. This was later followed by extended trials up to 265 km in Sulehalli in the Wadi-Vikarabad-Sanatnagar-Bidar section.

“Kavach demonstrated the suitability for automatic signalling in 2015 itself. The innovation of ‘M-communication technology’ triggered and advanced its deployment by a decade, providing the highest data security without waiting for the 4G radio system. However, the edge was lost as the project suffered setbacks on account of decision to opt for ETCS,” the sources claimed.

The Railway Board in July 2017 decided to opt for the ETCS Level 1,an “inferior and obsolete” technology, the sources said, for important routes, and Kavach for less important routes. The decision to opt out for ETCS Level 2 was taken in 2020, the sources said.

The COVID-19 pandemic halted the ETCS Level 2 tender, bringing Kavach to the forefront again. The system underwent passenger train trials in 2016, and product appraisal trails in 2018. Railway Minister Ashwini Vaishnaw, too, endorsed the indigenous system after witnessing the work in Vikarabad in 2022, when two trains on the same track were stopped 380 metres apart.

Kavach was not properly executed for about four years, with installation in the South Central Railway held up till July 2021, the sources said. The implementation was prioritised after the Balasore accident involving three trains in June 2023.

Kavach Version 4 is also reported to be facing some issues, including the Temporary Speed Restriction System, which are currently being worked out. “If the nitty-gritty issues are sorted out, it will be possible to equip the main trunk lines of about 10,000 km with the system in the next seven years,” the sources in the Railways said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.

  翻译: