The scaffold is down at last in Whitechapel on the Peter & Painter House reclad project undertaken between Stanta and key client Hill Partnerships and we are delighted with the results and how well the project was run between our companies. The reclad of this 2006 development involved removal & replacement of over 1,800m2 of Rockpanel cladding including Insulations, Boards, Breather membranes and more. Stanta also replaced soffits to all walkways and communal areas. It was delivered through close collaboration with our Hill Group UK Client, Architect (ATP group) design team and Stanta designers in support. Well done to all involved in delivery of the project from Stanta including Jason Millar, John McElhinney MCIOB & Florin Rebrisorean along with our excellent installation teams. Many thanks to Hill Partnerships for the order.
-
-
-
-
-