#Thoughts ~ YTL - UK Brabazon Timeline
PHASE 1 (Ongoing):
• 2016: Acquisition of Filton Airfield by YTL Power.
• 2018: Initial planning permission granted.
• 2023-Present: Construction of the first phase of homes underway.
- Over 150 homes already completed and occupied.
- 240 homes currently under construction.
PHASE 2 (Current Focus):
• Late February 2024: Revised masterplan approved by South Gloucestershire Council.
• 2024-Present: Implementation of the revised plan, including:
- Development of 6,500 homes (phased to align with transport improvements).
- Construction of commercial spaces, schools, hotels, and other amenities.
- Development of the 15-acre urban park.
Infrastructure improvements (transport, utilities, etc.).
PHASE 3 (Long-term):
• Ongoing and Future:
- Continued development and refinement of the Brabazon community.
- Ongoing maintenance and management of the development.
- Potential for future phases and expansions based on market demand and evolving needs.
KEY Considerations:
> Phased Development: The project is designed with a phased approach to ensure sustainability and minimize disruption.
> Transport Improvements: The timeline will be significantly influenced by the pace of transport infrastructure improvements, as outlined in the approved plans.
> Market Conditions: Economic factors, such as interest rates, housing demand, and construction costs, will also impact the project's timeline.
Estimated Overall Timeline — The entire Brabazon development is likely to take 15-20 years or more to fully complete. This is a long-term project with a focus on creating a sustainable and thriving community over the decades.